Construction Cost Calculator

Estimate villa building costs in Bali

Project Details

Good quality, modern finishes - $650/sqm

Total Cost

$178,400

Cost per sqm

$892

Timeline

8 months

Cost Breakdown

Building Construction (200 sqm x $650/sqm)$130,000
Swimming Pool (8m x 4m)$15,000
Landscaping & Garden$5,000
Architect Fee (8%)$10,400
Permits & IMB$3,000
Contingency (10%)$15,000
TOTAL PROJECT COST$178,400

Construction Guide for Bali

Required Permits

  • - IMB (Building Permit): $2,000-5,000, takes 2-4 months
  • - Environmental clearance if near rice fields or coast
  • - Village approval (banjar meeting)
  • - Architect drawings: Required for IMB application

Construction Timeline

  • - Design & permits: 2-4 months
  • - Foundation: 2-4 weeks
  • - Structure: 2-3 months
  • - Finishing: 2-4 months
  • - Total: 8-12 months for 200 sqm villa

Money-Saving Tips

  • - Use local materials (teak, lavastone, bamboo) - cheaper and authentic
  • - Simple design = lower costs (complex curves expensive)
  • - Hire local contractor vs. expat-run (30-50% cheaper)
  • - Buy materials direct from suppliers, not through contractor
  • - Two-story more economical than spreading out